Development Project

Overview

Following many months of consultation, demolition, construction and interior work, we are delighted to announce that, other than a few finishing touches, the extension of our facilities at the Wight School has finished!

The aims of the development project included:

Providing an enhanced environment for Harbury Pre-School and its provision of sessional care with:

Providing a more secure environment by:

To improve the DDA compliance of the facility with:

As well as improvements to the Pre-School facilities, the work also included the demolition of the old toilets to improve access to the car park.

The photographs below tell the whole story!

Photograph Diary

Photographs taken by Katy Spencer Hammon and Gael Conway

Day 1

Thursday 3 March 2011

yextension_005.jpg yextension_007.jpg z1-800.jpg yextension_009.jpg yextension_016.jpg yextension_015.jpg

Day 3

Groundworks dug out for the new extension

yextension_012.jpg yextension_013.jpg

Day 4

Partition wall going up across what used to be resource room to form new disabled toilet

ASCII ASCII

Day 5

Goodbye wire fence!

z6-800.jpg

Cutting doorway through

z4-800.jpg z8-800.jpg

z5-800.jpg z7-800.jpg

Building inspectors

z9-800.jpg

Day 6

Concrete pads for extension

z11-800.jpg

Day 10

Groundworks including walls and plumbing

z13-800.jpg

Day 11

New disabled toilet and a last look inside the old toilet block

ASCII ASCII

Day 12

Monday 14 March 2011

Demolition of the old toilet block - going…going…going…most definitely gone!

a3-800.jpg a4-800.jpg a5-800.jpg a6-800.jpg

Day 14

Disabled toilet fitted out and ready to use

b13-800.jpg

Day 16

Friday 18 March 2011

The development earns a mention in the local paper Leamington Courier

Meanwhile the existing brick extension is tidied up following the demolition work and work continues in preparation for the new extension

b1-800.jpg b2-800.jpg b3-800.jpg b4-800.jpg

Day 23

Preview photos of the extension (which is being built off-site)

b7-800.jpg b8-800.jpg b9-800.jpg b10-800.jpg b11-800.jpg

Day 26

Preparation continues for the extension which arrives in two days!

b5-800.jpg b6-800.jpg

Day 28

Wednesday 30 March 6.30am and the extension arrives!

First half

c1-800.jpg c2-800.jpg c3-800.jpg

Second half

c4-800.jpg c5-800.jpg c6-800.jpg

Both halves being lifted into place

ASCII ASCII

Minor adjustment

d11-800.jpg

A sneak look inside…children's toilets, disabled toilet, corridor, kitchen and resource room

ASCII ASCII ASCII d5-800.jpg d6-800.jpg

And on the outside…

d8-800.jpg d9-800.jpg

Day 29

Velux windows allow light to flood into library and extension, allow the existing library windows to be seen and give cubby holes for coats and storage

ASCII d7-800.jpg ASCII

Day 30

Exterior brick work completed

d1-800.jpg d2-800.jpg

Day 31

Working party - staff and friends help organise the new space

ASCII ASCII ASCII ASCII ASCII

GRAND OPENING!

Day 38 - Saturday 9 April 2011

ASCII ASCII ASCII ASCII ASCII

Some weeks later...

New extension features on our carnival float “Celebrations”

ASCII

August 2011

Work starts on the driveway

dw1-800.jpg dw2-800.jpg dw5-800.jpg

Dropped kerb being put in

dw3-800.jpg dw4-800.jpg

Tarmac going down

dw7-800.jpg dw8-800.jpg dw9-800.jpg 31.08.11_10_-800.jpg

Meanwhile, inside the main room…

…floor taken up and relaid…

23.08.11_5_-800.jpg 23.08.11_6_-800.jpg 30.08.11_1_-800.jpg

…and goodbye to the corner storage cupboards…

30.08.11_2_-800.jpg

…and yet more cleaning!

31.08.11-800.jpg 31.08.11_3_-800.jpg 31.08.11_1_-800.jpg

At last all cleaned and set up, and the children try out the new look classroom

floor.jpg

But it's not finished yet…

December 2011

Freshly decorated and new flooring goes down

Looking into the corner where the cupboards used to be

ASCII

Looking towards the door to the library

ASCII

TA-DA!!!

allready-800.jpg allready1-800.jpg allready2-800.jpg